A group of question marks sitting next to each other

PMP Exam Example Questions – Set 4

Question 1: Stakeholder Engagement

A project manager is leading a large infrastructure project with diverse stakeholders, including government officials, local businesses, and environmental groups. During a routine status meeting, a key stakeholder expresses dissatisfaction with the project’s progress, claiming their concerns are being ignored. This stakeholder has a high level of influence but a low interest in the project’s deliverables.
What should the project manager do next to manage this stakeholder effectively?

A. Increase the stakeholder’s engagement level by including them in detailed project decisions.
B. Develop a communication plan tailored to the stakeholder’s influence and concerns.
C. Log the stakeholder’s concerns in the risk register and escalate them to the sponsor.
D. Minimize interactions with this stakeholder to prevent further disruptions.


Question 2: Risk Management

During a software development project using Agile methodologies, a team identifies a potential risk of team burnout due to tight deadlines in the next sprint. The product owner suggests adding more resources to speed up work, but the Scrum Master is concerned about onboarding delays and team dynamics.
What should the project manager recommend?

A. Proceed with adding resources to prevent delays.
B. Allow the team to decide on an appropriate risk mitigation approach during sprint planning.
C. Use velocity data to adjust sprint capacity and reduce workload.
D. Update the risk register and accept the risk, as it is inherent in tight timelines.


Question 3: Schedule Management

A project is behind schedule due to delays in securing required permits. The project manager decides to compress the schedule by overlapping some design and construction phases.
What technique is the project manager using?

A. Crashing
B. Fast tracking
C. Resource leveling
D. Critical path method


Question 4: Scope Management

A stakeholder requests additional functionality that was not included in the initial scope but is likely to increase customer satisfaction. The project is nearing completion, and the sponsor has advised against extending the timeline.
What should the project manager do first?

A. Reject the request since it is out of scope.
B. Evaluate the change request through the Perform Integrated Change Control process.
C. Escalate the request to the sponsor for a decision.
D. Add the functionality if it can be completed within the existing budget.


Question 5: Agile Roles

In an Agile project, the product owner consistently misses sprint planning meetings, leaving the team uncertain about priorities. What should the Scrum Master do?

A. Take over the product owner’s role temporarily to ensure progress.
B. Discuss the issue with the product owner and reiterate their responsibilities.
C. Prioritize items based on the team’s understanding and continue with the sprint.
D. Escalate the issue to the sponsor to replace the product owner.


Question 6: Communication Management

A project involves a global team spread across multiple time zones. One team member in a different time zone is consistently missing virtual stand-ups. What should the project manager do?

A. Record meetings and share them with the absent team member.
B. Conduct stand-ups at a time convenient for the entire team.
C. Exclude the team member from stand-ups and provide updates later.
D. Rotate meeting times to accommodate different time zones.


Question 7: Cost Management

During project execution, the project manager discovers that the cost performance index (CPI) is 0.85. What does this indicate about the project?

A. The project is under budget.
B. The project is over budget.
C. The project is ahead of schedule.
D. The project is within acceptable budget variance.


Question 8: Quality Control

A project team discovers a recurring defect during product testing. What should the project manager do first?

A. Perform root cause analysis to identify the source of the defect.
B. Update the risk register to reflect the defect.
C. Escalate the issue to the quality control department.
D. Reassign resources to fix the defect.


Question 9: Procurement Management

A vendor fails to deliver a critical component on time, jeopardizing the project timeline. The vendor cites issues with their subcontractor. What should the project manager do first?

A. Escalate the issue to the sponsor to manage the vendor.
B. Review the terms of the procurement contract for remedies.
C. Identify alternative vendors to source the component.
D. Negotiate directly with the subcontractor.


Question 10: Leadership in Agile Projects

During a sprint retrospective, the team reveals that they are demotivated due to micromanagement by a senior developer. What should the project manager do?

A. Replace the senior developer with another team member.
B. Facilitate a workshop on servant leadership principles.
C. Allow the team to resolve the issue through self-organization.
D. Schedule one-on-one meetings to understand individual concerns.


Question 11: Stakeholder Management

A sponsor provides inconsistent feedback, causing delays in project approvals. The team is unsure how to proceed. What should the project manager do?

A. Escalate the issue to the governance board.
B. Clarify expectations with the sponsor and establish a structured review process.
C. Proceed with work based on the project manager’s best judgment.
D. Assign a team member to manage sponsor communications.


Question 12: Risk Monitoring

Midway through project execution, a previously identified risk materializes, causing significant delays. What should the project manager do next?

A. Implement the risk response plan.
B. Update the risk register and conduct a new risk analysis.
C. Notify stakeholders and escalate the issue.
D. Add the risk to the issue log and assign an owner.


Question 13: Team Development

During a team-building exercise, a conflict arises between two team members over their roles. What should the project manager do?

A. Mediate the conflict and clarify roles and responsibilities.
B. Allow the team to self-organize and resolve the conflict.
C. Assign the roles based on the project manager’s judgment.
D. Escalate the issue to the functional manager.


Question 14: Value Delivery

A project manager is transitioning from traditional waterfall to Agile practices. How can the project manager ensure value delivery in the new approach?

A. Use earned value management (EVM) to measure performance.
B. Prioritize customer needs and feedback during sprint reviews.
C. Ensure all project scope is defined upfront.
D. Focus on reducing costs and delivering under budget.


Question 15: Integration Management

The project sponsor requests that the project manager add a new deliverable late in the project. This deliverable was not part of the project charter but is critical for the project’s success. What should the project manager do?

A. Reject the request, as it was not included in the charter.
B. Add the deliverable if resources and time permit.
C. Evaluate the impact of the change and process it through change control.
D. Ask the team to prioritize the deliverable over existing tasks.


Question 16: Resource Management

A key team member resigns unexpectedly during project execution, creating a resource gap. The project manager immediately consults the resource management plan to identify alternatives. What should the project manager do next?

A. Reassign tasks to existing team members and adjust the schedule.
B. Escalate the issue to the sponsor for immediate resolution.
C. Collaborate with HR to onboard a replacement as soon as possible.
D. Update the risk register to reflect the impact of resource loss.


Question 17: Conflict Management

Two senior developers disagree over the implementation approach for a critical feature, delaying the team’s progress. Both approaches align with project requirements but differ in technical complexity.
What should the project manager do?

A. Facilitate a discussion to reach a consensus between the developers.
B. Decide on the approach to ensure progress and communicate the decision.
C. Assign the decision-making authority to the product owner.
D. Schedule a brainstorming session to explore a third alternative.


Question 18: Monitoring KPIs

A project manager notices that the schedule variance (SV) is negative, and the project is 10% behind schedule. The project sponsor demands immediate corrective action.
What should the project manager do first?

A. Update the schedule baseline and share it with the sponsor.
B. Analyze the critical path to identify potential delays.
C. Request additional resources to recover the schedule.
D. Adjust the scope to reduce deliverables and meet the timeline.


Question 19: Change Control

A customer requests an enhancement that will improve the final product’s usability but will extend the project timeline. The project team has the capacity to implement the change without exceeding the budget.
What should the project manager do next?

A. Implement the change since it adds value to the product.
B. Evaluate the impact of the change request and follow the change control process.
C. Reject the request, as it impacts the timeline.
D. Prioritize the enhancement for a future phase of the project.


Question 20: Governance

The governance board is concerned about a lack of visibility into project progress. The project manager has provided detailed weekly reports, but the board requests a simpler format.
What should the project manager do?

A. Maintain the current reporting format to ensure accuracy.
B. Design a dashboard with high-level metrics to address the board’s needs.
C. Assign a team member to create custom reports for the board.
D. Schedule a meeting to explain the detailed reports.


Question 21: Stakeholder Prioritization

During stakeholder analysis, the project manager identifies a stakeholder with low power but high interest. How should this stakeholder be managed?

A. Monitor them with minimal engagement.
B. Keep them informed and address their concerns.
C. Involve them in key decision-making processes.
D. Escalate their concerns to higher-priority stakeholders.


Question 22: Quality Assurance

A project team has completed the design phase and is preparing to start development. The quality assurance team recommends a peer review of the design documents before proceeding.
What is the primary benefit of this recommendation?

A. Ensuring the design aligns with quality standards.
B. Reducing the overall project cost.
C. Accelerating the development phase.
D. Avoiding scope creep during development.


Question 23: Adaptive Project Management

A company is transitioning to a hybrid project management model that combines Agile and predictive approaches. How should the project manager ensure effective implementation?

A. Use Agile for all deliverables to reduce complexity.
B. Assign separate teams to manage Agile and predictive components.
C. Tailor practices to the project’s needs and align stakeholder expectations.
D. Follow the predictive approach for better control of deliverables.


Question 24: Integration of Lessons Learned

At the close of a project, the project manager conducts a lessons learned session. How should the project manager ensure the lessons are applied to future projects?

A. Archive the lessons in the organizational process assets (OPA).
B. Share the lessons learned with the project sponsor.
C. Recommend changes to organizational processes based on the findings.
D. Present the lessons learned during team training sessions.


Question 25: Agile Mindset

A stakeholder in an Agile project is concerned about the lack of detailed upfront planning. They are used to traditional project management and demand a comprehensive plan. How should the project manager address this concern?

A. Explain that Agile prioritizes adaptability over upfront planning.
B. Develop a detailed plan to satisfy the stakeholder’s expectations.
C. Highlight the value of incremental delivery and early feedback.
D. Transition the project to a predictive approach to address the stakeholder’s needs.

Please share your view on the  PMP Exam Example Questions set. Like and share the questions.

PMP Exam Example Questions
PMP Questions and Answers

PMP Questions and Answers – Set 3, Ultra Tough PMP Question Bank Set

Below are 50 PMP Questions and Answers designed to help you prepare effectively for the exam. Explanations for all correct answers are provided at the end of the questions to enhance your understanding and boost your confidence.

1. During project initiation, the project sponsor asks for a summary of the financial justification for the project. Which document should you provide?

2. Which of the following is NOT typically a purpose of the project charter?

  • A. Formally authorize the project
  • B. Define the WBS for the project
  • C. Assign responsibility to the project manager
  • D. Provide high-level project objectives

3. During stakeholder analysis, you identify a stakeholder who has high power but low interest. What is the recommended strategy for managing this stakeholder?

  • A. Keep satisfied
  • B. Monitor closely
  • C. Manage actively
  • D. Keep informed

4. What is the primary benefit of the “identify stakeholders” process?

  • A. Determining stakeholder influence and requirements
  • B. Documenting high-level risks
  • C. Developing the stakeholder engagement plan
  • D. Creating the assumptions log

5. A project manager is tasked with ensuring the project aligns with organizational strategic goals. What document provides this alignment?

  • A. Project Scope Statement
  • B. Benefits Management Plan
  • C. Enterprise Environmental Factors
  • D. Project Charter

6. In an agile project, who is primarily responsible for prioritizing work items in the backlog?

  • A. Scrum Master
  • B. Development Team
  • C. Product Owner
  • D. Agile Coach

7. Which of the following is typically a high-level deliverable created during project initiation?

  • A. Scope Baseline
  • B. Project Charter
  • C. Issue Log
  • D. Work Breakdown Structure

8. Which input is necessary for the “develop project charter” process?

  • A. Organizational Process Assets
  • B. Milestone List
  • C. Issue Log
  • D. Resource Calendar

9. What is the primary output of the “define scope” process?

  • A. Scope Baseline
  • B. Project Management Plan
  • C. Work Breakdown Structure (WBS)
  • D. Requirements Traceability Matrix

10. A project team is estimating activity durations using a three-point estimation technique. What is the formula for the PERT weighted average?

  • A. (O+4M+P)/6(O + 4M + P) / 6(O+4M+P)/6
  • B. (O+M+P)/3(O + M + P) / 3(O+M+P)/3
  • C. (P−O)/6(P – O) / 6(P−O)/6
  • D. 4M+(O+P)/34M + (O + P) / 34M+(O+P)/3

11. Which component of the project management plan defines how scope changes will be managed?

  • A. Scope Management Plan
  • B. Change Control Plan
  • C. Requirements Management Plan
  • D. Schedule Management Plan

12. When developing a quality management plan, the team refers to organizational process assets. Which of the following would NOT be considered an organizational process asset?

  • A. Quality standards from a previous project
  • B. Historical project performance data
  • C. Quality assurance policies
  • D. Government regulations

13. During risk planning, you categorize risks based on their causes. This is an example of:

  • A. Qualitative Risk Analysis
  • B. Risk Breakdown Structure (RBS)
  • C. Quantitative Risk Analysis
  • D. Risk Mitigation Planning

14. What is the primary goal of the Plan Procurement Management process?

  • A. Select suppliers for the project
  • B. Establish guidelines for managing procurements
  • C. Issue procurement contracts
  • D. Document market research findings

15. A team is planning activities for an agile project and uses velocity as a key planning metric. What does velocity measure?

  • A. Time taken to complete a sprint
  • B. The number of features delivered in a sprint
  • C. The team’s capacity to deliver story points per sprint
  • D. The cost of completing a sprint

16. Which of the following is NOT an input to the “develop schedule” process?

  • A. Resource Requirements
  • B. Project Scope Statement
  • C. Activity List
  • D. Resource Leveling

17. What is the purpose of the risk register?

  • A. Track the implementation of risk responses
  • B. Document identified risks and their characteristics
  • C. Define strategies for managing risks
  • D. Record lessons learned related to risks

18. Which of the following is NOT a technique for defining project activities?

  • A. Rolling Wave Planning
  • B. Expert Judgment
  • C. Critical Path Method
  • D. Decomposition

19. When is the stakeholder engagement plan developed?

  • A. During the initiating phase
  • B. During the planning phase
  • C. During the executing phase
  • D. During the monitoring and controlling phase

20. A project manager is calculating the contingency reserve. What tool or technique would be most useful for this task?

  • A. Expert Judgment
  • B. Monte Carlo Analysis
  • C. Ishikawa Diagram
  • D. Delphi Technique

21. What is the primary purpose of a daily stand-up in agile project management?

  • A. Review completed deliverables
  • B. Monitor team progress and remove impediments
  • C. Evaluate team velocity and adjust iterations
  • D. Identify new risks

22. A project manager notices that team members are completing tasks but not updating the task status in the project management software. What should the project manager do?

  • A. Update the tasks personally
  • B. Provide additional training to the team
  • C. Escalate the issue to the sponsor
  • D. Remind the team of the importance of real-time updates

23. During execution, a project manager discovers that a contractor has not met a key deliverable deadline. What is the project manager’s next step?

  • A. Issue a change request to adjust the schedule
  • B. Escalate the issue to the sponsor
  • C. Conduct a procurement performance review
  • D. Terminate the contractor’s agreement

24. In agile projects, how are deliverables verified and accepted?

  • A. During iteration retrospectives
  • B. By stakeholders in sprint reviews
  • C. During daily stand-ups
  • D. By the Product Owner in the project closure phase

25. A conflict arises between two team members regarding task ownership. What is the project manager’s most appropriate action?

  • A. Escalate the issue to the functional manager
  • B. Apply conflict resolution techniques to address the issue
  • C. Reassign tasks to prevent further conflict
  • D. Conduct a formal disciplinary review

26. What is the primary focus of earned value management (EVM)?

  • A. Estimate activity durations
  • B. Track team performance during agile sprints
  • C. Measure project performance against scope, cost, and schedule baselines
  • D. Evaluate the quality of deliverables

27. A project has a cost performance index (CPI) of 1.1 and a schedule performance index (SPI) of 0.9. What does this indicate?

  • A. The project is under budget but behind schedule.
  • B. The project is over budget but ahead of schedule.
  • C. The project is both under budget and ahead of schedule.
  • D. The project is both over budget and behind schedule.

28. A team member informs the project manager that additional resources are needed to stay on schedule. What is the first action the project manager should take?

  • A. Request additional budget from the sponsor.
  • B. Perform a resource leveling analysis.
  • C. Issue a change request for additional resources.
  • D. Evaluate the schedule to determine the impact of resource constraints.

29. The control chart for a manufacturing process shows points that are outside the upper control limit. What does this indicate?

  • A. The process is within acceptable limits.
  • B. The process is statistically out of control.
  • C. The process requires no immediate action.
  • D. The process is operating at an ideal level of quality.

30. A project is tracking SPI and CPI values regularly. Which tool is the project manager using?

  • A. Schedule Network Analysis
  • B. Earned Value Management
  • C. Resource Leveling
  • D. Critical Chain Method

31. A key deliverable is rejected during a formal inspection. What is the best course of action for the project manager?

  • A. Adjust the project scope baseline.
  • B. Schedule a lessons-learned session.
  • C. Document the issue and initiate corrective actions.
  • D. Communicate the rejection to the sponsor immediately.

32. While performing qualitative risk analysis, you rank risks based on probability and impact. This approach:

  • A. Requires extensive mathematical modeling.
  • B. Creates a prioritized risk list for action.
  • C. Relies exclusively on stakeholder input.
  • D. Focuses on cost over schedule risks.

33. A stakeholder requests additional functionality beyond the project’s approved scope. The project manager should:

  • A. Accept the request if it will benefit the project.
  • B. Escalate the request to the project sponsor.
  • C. Submit the request to the Change Control Board (CCB).
  • D. Include the change in the next progress report.

34. What is the primary purpose of variance analysis in project monitoring?

  • A. Identify areas where processes can be streamlined.
  • B. Determine the root cause of deviations from the baseline.
  • C. Develop responses for high-priority risks.
  • D. Create contingency reserves for future phases.

35. The project manager receives a report showing CPI = 0.9 and SPI = 1.1. What should they prioritize?

  • A. Controlling costs
  • B. Revising the schedule
  • C. Managing risks
  • D. Accelerating project activities

36. A project manager notices that changes are being implemented without approval. What process is being bypassed?

  • A. Integrated Change Control
  • B. Validate Scope
  • C. Perform Quality Control
  • D. Direct and Manage Project Work

37. During control quality, a project manager identifies a recurring defect in deliverables. What tool would help determine the root cause?

  • A. Pareto Chart
  • B. Control Chart
  • C. Ishikawa Diagram
  • D. Histogram

38. During project closure, the team realizes that an issue from execution remains unresolved. What is the best action?

  • A. Close the project without addressing the issue.
  • B. Document the issue in the lessons learned register.
  • C. Reopen the project to resolve the issue.
  • D. Request additional funding to address the issue.

39. What is the primary purpose of a final project audit?

  • A. Validate the project’s compliance with quality standards.
  • B. Formally release team resources.
  • C. Assess the project’s success and identify lessons learned.
  • D. Archive all project documents.

40. In an agile project, the retrospective meeting serves what purpose?

  • A. Approve completed deliverables for the sprint.
  • B. Plan the next sprint’s tasks.
  • C. Discuss team performance and process improvements.
  • D. Reassess the project backlog priorities.

41. Which document captures all details of project deliverables handed over to operations?

  • A. Project Management Plan
  • B. Final Report
  • C. Transition Plan
  • D. Benefits Management Plan

42. A project team has completed all deliverables, and the project sponsor signs off on final acceptance. What is the next step?

  • A. Conduct a stakeholder review meeting.
  • B. Update the project charter.
  • C. Release project resources and close procurements.
  • D. Perform a root cause analysis on unresolved issues.

43. During a final stakeholder meeting, a key stakeholder expresses dissatisfaction with the project outcome. What should the project manager do?

  • A. Escalate the concern to the sponsor.
  • B. Document the feedback in the final report.
  • C. Revise the deliverables to meet the stakeholder’s expectations.
  • D. Exclude the stakeholder from the closure process.

44. Which activity is NOT part of the Close Project or Phase process?

  • A. Conducting a post-project review
  • B. Validating scope with stakeholders
  • C. Ensuring deliverables are accepted
  • D. Updating the risk register

45. What is a key benefit of a lessons learned register?

  • A. Documents the root cause of project risks
  • B. Provides a historical record for future projects
  • C. Validates the success criteria of the project
  • D. Defines the transition process to operations

46. In an agile project, what is the primary role of the Scrum Master?

  • A. Define acceptance criteria for user stories.
  • B. Prioritize the backlog to ensure business value.
  • C. Remove impediments and support the development team.
  • D. Approve sprint goals and deliverables.

47. A product owner adjusts backlog priorities during a sprint. How should the Scrum Master respond?

  • A. Allow the adjustment if it aligns with stakeholder needs.
  • B. Prevent changes until the sprint is complete.
  • C. Escalate the issue to the project sponsor.
  • D. Update the team on the new priorities immediately.

48. Which of the following is an output of iteration planning?

  • A. Sprint Backlog
  • B. Product Roadmap
  • C. Definition of Done
  • D. Burnup Chart

49. In agile, what is the purpose of a “spike”?

  • A. Test the feasibility of a technical solution.
  • B. Address a high-priority risk during sprint planning.
  • C. Estimate user stories during backlog refinement.
  • D. Resolve team conflicts related to task allocation.

50. During sprint reviews, the development team demonstrates completed features. Who is responsible for accepting these features?

  • A. Product Owner
  • B. Scrum Master
  • C. Stakeholders
  • D. Team Lead

PMP Questions and Answers

Download the PMP Questions and Answers PDF

PMP Question Bank

PMP Questions and Answers – Set 2, Ultra Tough PMP Question Bank Set of 50

Preparing for the PMP exam requires a strategic approach, and practicing with a reliable PMP Question Bank is essential. Our ultra-tough set of 50 PMP questions and answers will challenge your understanding of key concepts and sharpen your problem-solving skills. Each question aligns with the latest exam standards, helping you build confidence and ace the test. Start your journey to PMP success today!

PMP Question Bank

Question 1:
A project manager is leading a complex software development project with a cross-functional team spread across multiple time zones. The sponsor has asked for bi-weekly status reports on key deliverables, but some team members are resistant to documenting their progress, claiming it distracts from the work. The project manager wants to balance sponsor requirements with team efficiency. What should the project manager do first?

A) Inform the team that status reports are mandatory and must be submitted as per the sponsor’s request.
B) Schedule a meeting with the sponsor to discuss reducing the frequency of status reports.
C) Implement automated reporting tools to reduce the burden on the team.
D) Review the communication management plan and adapt it to the needs of both the sponsor and the team.


Question 2:
During a sprint review meeting, the product owner expresses dissatisfaction with a feature that was delivered, even though it met the previously agreed-upon acceptance criteria. The product owner argues that the feature doesn’t align with the overall vision for the product. What should the project manager do in this situation?

A) Ask the product owner to formally change the acceptance criteria for future sprints.
B) Organize a follow-up meeting to gather feedback and revisit the product vision.
C) Escalate the issue to the project sponsor for clarification on the vision.
D) Remind the product owner that the team followed the criteria and ask them to accept the work.


Question 3:
A project team is using an Agile approach to develop a new mobile app. Midway through the project, the customer requests a major change to the app’s core functionality. This will significantly impact the project scope and timeline. How should the project manager handle this situation?

A) Ask the customer to submit a formal change request and assess the impact on scope, time, and cost.
B) Refuse the change request, as it will delay the project and disrupt the team’s progress.
C) Incorporate the change into the current sprint to avoid additional delays.
D) Collaborate with the team and product owner to evaluate the change and adjust the backlog accordingly.


Question 4:
A project manager has identified a major risk that could potentially delay the project by two months. After conducting a qualitative risk analysis, the project manager ranks the risk as high probability and high impact. What should the project manager do next?

A) Escalate the risk to senior management and request additional resources to mitigate the impact.
B) Develop a risk response plan that includes both preventive actions and contingency reserves.
C) Update the risk register and continue to monitor the risk in future project meetings.
D) Transfer the risk to a third party through a contractual agreement.


Question 5:
A project manager overseeing a construction project realizes that key project milestones are being delayed due to frequent change orders from the client. What is the best way to manage these ongoing changes while maintaining project progress?

A) Implement a strict change control process and reject any further changes.
B) Assign a change control board to review, approve, or reject changes based on their impact.
C) Accept all changes as long as they are within the project’s budget and time constraints.
D) Ask the client to limit change requests to avoid further delays.


Question 6:
A new project manager has been assigned to a project that is nearing completion. However, the stakeholders are unhappy with some of the deliverables. The project manager wants to ensure that these issues are addressed without delaying the project further. What should the project manager do first?

A) Conduct a stakeholder analysis to understand their expectations and concerns.
B) Initiate a formal change request to rework the problematic deliverables.
C) Review the project’s acceptance criteria to ensure alignment with stakeholder expectations.
D) Meet with the project sponsor to discuss how to handle the situation.


Question 7:
A project is in its final phase, and a key vendor is unable to deliver critical materials on time due to a supply chain issue. This delay will push the project past its deadline. What should the project manager do?

A) Escalate the issue to senior management and request an extension of the project deadline.
B) Work with the procurement team to identify alternative suppliers and mitigate the delay.
C) Issue a change request to update the project schedule and communicate the delay to stakeholders.
D) Negotiate with the vendor to expedite the delivery at an additional cost.


Question 8:
A project manager is working with a geographically dispersed team using Agile practices. Some team members are having difficulty attending daily stand-ups due to time zone differences. What is the best way to address this issue?

A) Record the stand-up meetings so team members can review them later.
B) Schedule separate stand-up meetings for each time zone.
C) Use asynchronous communication tools and allow team members to update their progress at different times.
D) Rotate the meeting time every week to accommodate all team members.


Question 9:
In the middle of a project, the project manager realizes that a key stakeholder has not been actively involved in recent discussions, and their input is critical for the project’s success. How should the project manager address this situation?

A) Contact the stakeholder directly and request their immediate involvement.
B) Review the stakeholder engagement plan and adjust strategies to re-engage the stakeholder.
C) Escalate the issue to the project sponsor to gain the stakeholder’s attention.
D) Continue the project without the stakeholder’s input and document their absence.


Question 10:
A project manager is leading a project to upgrade a company’s IT infrastructure. Halfway through the project, a significant technological advancement is announced that could make the current project solution obsolete. What should the project manager do?

A) Ignore the new technology and continue with the current project plan.
B) Immediately halt the project and propose adopting the new technology.
C) Perform an impact analysis to evaluate how the new technology could affect the project.
D) Consult the project sponsor and recommend canceling the project.


Question 11:
During a project, the team realizes that one of the key tasks on the critical path has been delayed, jeopardizing the project’s delivery date. The team suggests fast-tracking some activities to recover lost time. What is the primary risk of fast-tracking in this situation?

A) Increased costs due to additional resources.
B) Increased likelihood of rework and quality issues.
C) Reduced team morale due to the increased workload.
D) Additional risks from overlapping project activities.


Question 12:
A project is ahead of schedule, and the sponsor suggests reassigning some resources to another critical project. The project manager is concerned that removing resources could impact future work. How should the project manager respond?

A) Accept the sponsor’s request and reassign the resources immediately.
B) Conduct a resource leveling analysis to assess the impact of reassigning resources.
C) Request that the sponsor delay reassigning resources until the project is complete.
D) Reject the sponsor’s request to ensure that the project remains ahead of schedule.


Question 13:
A project manager is leading a high-priority project, and the customer has requested that all deliverables meet a specific set of quality standards. The team has had trouble meeting these standards, resulting in frequent rework. What should the project manager do to address this issue?

A) Increase the frequency of quality audits to catch issues early.
B) Review the quality management plan and provide additional training to the team.
C) Add more resources to the project to help with quality control.
D) Negotiate with the customer to relax the quality standards.


Question 14:
A project manager is leading a multi-year project, and the client has recently introduced a requirement for all project deliverables to comply with a new set of regulatory standards. How should the project manager handle this new requirement?

A) Reject the new requirement, as it was not part of the original project scope.
B) Submit a change request and assess the impact on the project scope, schedule, and budget.
C) Modify the deliverables to meet the new standards without formal approval.
D) Escalate the issue to the project sponsor and ask for additional funding.


Question 15:
A project sponsor informs the project manager that a key regulatory requirement was missed during the project planning phase, and the project must now be delayed to address it. How should the project manager respond?

A) Accept the delay and update the project schedule to reflect the new requirement.
B) Initiate a root cause analysis to identify how the requirement was missed.
C) Escalate the issue to the project sponsor and request additional resources to avoid delays.
D) Perform a risk analysis to assess the impact of incorporating the requirement.


Question 16:
During a project to develop a new product, the customer requests additional features that were not part of the original scope. These features will require a significant amount of additional work. What should the project manager do first?

A) Reject the request, as it is outside the original scope.
B) Submit a change request and assess the impact on scope, time, and cost.
C) Incorporate the additional features into the current work to keep the customer happy.
D) Ask the team to work overtime to accommodate the customer’s request.


Question 17:
A project manager is using earned value management (EVM) to track project performance. The project’s cost performance index (CPI) is 0.85, and the schedule performance index (SPI) is 0.95. What do these values indicate about the project?

A) The project is under budget and slightly behind schedule.
B) The project is over budget and slightly behind schedule.
C) The project is under budget and slightly ahead of schedule.
D) The project is over budget and slightly ahead of schedule.


Question 18:
The project team is using a Kanban board to manage their work. Recently, the board has been cluttered with tasks, and the team is struggling to prioritize their work. What should the project manager do?

A) Limit the work in progress (WIP) to prevent overload.
B) Remove low-priority tasks from the board to reduce clutter.
C) Implement daily stand-ups to help the team manage their tasks.
D) Assign a team member to monitor the board and reassign tasks as necessary.


Question 19:
A project sponsor is concerned about potential delays in a software development project due to dependencies on external vendors. The project manager wants to minimize the risk of vendor delays impacting the critical path. What should the project manager do?

A) Add extra float to activities that depend on vendor deliverables.
B) Use procurement contracts that include penalties for late delivery.
C) Schedule regular meetings with vendors to monitor their progress.
D) Negotiate with vendors to ensure that all critical tasks are completed early.


Question 20:
During a project review, the project manager discovers that the project’s burn-down chart shows a steady decline in work completed, and the team is not meeting their sprint goals. What should the project manager do?

A) Increase the number of team members to speed up work completion.
B) Reevaluate the team’s capacity and adjust the sprint goals accordingly.
C) Conduct a root cause analysis to determine why the team is not meeting their goals.
D) Shorten the sprint length to improve the team’s focus on tasks.


Question 21:
A project manager is leading a software development project using Scrum. The team is struggling to complete the user stories within the sprint. The project manager wants to improve the team’s velocity. What should the project manager do?

A) Break down user stories into smaller tasks that can be completed within a sprint.
B) Add more team members to increase the team’s capacity.
C) Extend the sprint length to give the team more time to complete their work.
D) Reduce the number of user stories included in each sprint.


Question 22:
During a project to develop a new product, the customer has expressed concerns about the project’s direction and requested frequent updates on progress. How should the project manager handle this request?

A) Increase the frequency of formal status reports to keep the customer informed.
B) Schedule regular meetings with the customer to provide updates and gather feedback.
C) Assign a team member to be the main point of contact for customer updates.
D) Implement a change control process to manage the customer’s requests.


Question 23:
A project manager is working with a team to develop a new feature for an existing product. Midway through the project, the customer requests that the feature be completely redesigned. What should the project manager do?

A) Explain to the customer that the redesign will delay the project and impact the budget.
B) Submit a change request and assess the impact of the redesign on the project’s scope, schedule, and cost.
C) Proceed with the redesign and adjust the project plan to accommodate the changes.
D) Refuse the redesign request, as it is outside the original scope.


Question 24:
A project is in its early stages, and the project manager is working with the team to develop a risk management plan. What is the primary purpose of a risk management plan?

A) To identify potential risks that could impact the project.
B) To define how risks will be monitored and controlled throughout the project.
C) To outline risk response strategies for known risks.
D) To create a risk register that will be updated throughout the project.


Question 25:
A project is behind schedule, and the project manager has requested that the team work overtime to catch up. However, the team is already experiencing low morale due to high workloads. What should the project manager do?

A) Continue with the overtime request to meet the project deadline.
B) Reevaluate the project schedule and consider extending the deadline.
C) Hire additional resources to relieve the workload on the team.
D) Schedule a team-building activity to improve morale before continuing with overtime.

Question 26:
During a project’s execution phase, a team member identifies an opportunity to improve a process that could reduce costs by 15%. However, implementing this improvement will require a temporary halt in production, which could delay the project by one week. How should the project manager handle this?

A) Approve the process improvement as the cost savings outweigh the delay.
B) Submit a change request to assess the impact of the delay on the overall project.
C) Reject the suggestion, as the project is already under a tight deadline.
D) Escalate the issue to the project sponsor for approval.


Question 27:
A project manager is working on a project to develop new software for a client. During the testing phase, the team identifies several defects that will require rework. This rework will push the project past the agreed-upon delivery date. What should the project manager do first?

A) Inform the client about the defects and negotiate a new delivery date.
B) Instruct the team to work overtime to meet the original deadline.
C) Perform an impact analysis to determine how the defects will affect the schedule.
D) Add additional resources to the project to accelerate the rework.


Question 28:
A project manager is managing a large construction project, and a major stakeholder is consistently requesting changes to the project scope. These changes are small but frequent and are starting to affect the project schedule. What should the project manager do?

A) Escalate the issue to the project sponsor for resolution.
B) Update the schedule to reflect the impact of each change request.
C) Enforce the change control process to manage and assess each request’s impact on time and cost.
D) Accept the changes as long as they do not affect the project’s critical path.


Question 29:
A project manager is leading a high-profile project with multiple stakeholders who have conflicting interests. The project sponsor asks the project manager to prioritize one stakeholder’s requests over others to meet an aggressive deadline. What should the project manager do?

A) Comply with the sponsor’s request to maintain a good relationship with the sponsor.
B) Balance the requests of all stakeholders and ensure that no stakeholder is favored.
C) Escalate the issue to senior management to resolve the conflict between stakeholders.
D) Facilitate a stakeholder meeting to discuss the conflicting interests and seek alignment.


Question 30:
A project team is in the execution phase of a software development project. The project sponsor has requested several features that were not included in the original scope, and the project manager is concerned about scope creep. What is the most appropriate action for the project manager to take?

A) Add the requested features to the project to keep the sponsor happy.
B) Use the change control process to evaluate the impact of the new features on the project’s scope, schedule, and cost.
C) Refuse the request, as it falls outside of the agreed-upon scope.
D) Accept the sponsor’s request and adjust the project baseline accordingly.


Question 31:
A project manager is overseeing a project that involves multiple vendors. One vendor has consistently delivered their work late, causing delays in the project. What should the project manager do to address this issue?

A) Terminate the contract with the vendor and find a replacement.
B) Work with the vendor to create a recovery plan to get the project back on track.
C) Escalate the issue to senior management and request additional resources.
D) Negotiate a penalty clause in the contract to hold the vendor accountable for future delays.


Question 32:
A project manager notices that the project team is frequently missing deadlines for completing tasks, despite the schedule being realistic. Upon investigation, the project manager finds that team members are unclear about their responsibilities. What should the project manager do to address this issue?

A) Review and clarify roles and responsibilities with the team to ensure alignment.
B) Conduct a performance review to identify underperforming team members.
C) Implement a stricter reporting process to monitor task completion more closely.
D) Reassign tasks to ensure they are completed by more experienced team members.


Question 33:
During a project status meeting, the project manager realizes that several high-priority risks identified in the risk register have not been addressed. What should the project manager do next?

A) Update the risk register and continue monitoring the risks during future meetings.
B) Escalate the unaddressed risks to the project sponsor and request additional resources.
C) Review the risk response strategies and assign team members to address the high-priority risks immediately.
D) Add additional contingency reserves to the project budget to mitigate the risks.


Question 34:
A project manager is working on a project with a tight deadline. The team suggests using a new, untested technology that could speed up delivery but may introduce unforeseen risks. How should the project manager proceed?

A) Approve the use of the new technology to meet the tight deadline.
B) Reject the suggestion and stick with the current technology to avoid risks.
C) Perform a risk analysis to evaluate the potential impact of using the new technology.
D) Present the suggestion to the project sponsor for final approval.


Question 35:
A project is experiencing frequent changes to the scope, which is causing delays and increasing costs. The project manager wants to improve control over these changes. What is the best approach to manage this situation?

A) Implement a more rigid change control process to evaluate the impact of changes.
B) Ask the customer to limit the number of changes to avoid further delays.
C) Escalate the issue to senior management to request additional resources.
D) Review the project scope and re-baseline the schedule to accommodate future changes.


Question 36:
A project manager is leading a cross-functional team, and some team members are consistently completing their tasks late. These delays are causing bottlenecks in other areas of the project. What should the project manager do to address this situation?

A) Implement a stricter deadline policy for team members who are missing deadlines.
B) Use a team-building activity to improve collaboration and communication.
C) Meet with the team members individually to understand the root causes of the delays and provide support.
D) Assign additional resources to the tasks that are consistently late to meet the deadlines.


Question 37:
A project manager is using earned value management (EVM) to track project performance. The cost variance (CV) is negative, and the schedule variance (SV) is also negative. What does this indicate about the project?

A) The project is under budget but behind schedule.
B) The project is over budget but ahead of schedule.
C) The project is over budget and behind schedule.
D) The project is under budget and ahead of schedule.


Question 38:
A project manager is preparing for a project kick-off meeting. One of the key stakeholders is unable to attend due to scheduling conflicts. What should the project manager do?

A) Postpone the meeting until the stakeholder is available.
B) Hold the meeting as scheduled and provide the stakeholder with the meeting minutes.
C) Reschedule the meeting with a smaller group of stakeholders.
D) Hold a separate meeting with the stakeholder after the kick-off meeting.


Question 39:
A project manager is managing a project in a highly regulated industry, and new regulations are introduced midway through the project. How should the project manager respond to this change?

A) Perform a risk analysis to assess how the new regulations will impact the project.
B) Immediately update the project’s scope to include compliance with the new regulations.
C) Request additional funding from the project sponsor to cover the cost of compliance.
D) Escalate the issue to senior management for guidance on how to proceed.


Question 40:
A project manager is leading a project to develop a new product. During a sprint review, the customer expresses dissatisfaction with the progress and requests changes that would significantly alter the project’s scope. How should the project manager respond?

A) Implement the requested changes to satisfy the customer and avoid conflict.
B) Explain the impact of the changes and submit a change request to evaluate the impact on scope, time, and cost.
C) Reject the changes, as they fall outside of the agreed-upon scope.
D) Ask the team to accommodate the changes without delaying the project.


Question 41:
A project manager is managing a project with both predictive and Agile components. The team is struggling to balance the two approaches, and progress is slow. What is the best way for the project manager to address this challenge?

A) Prioritize the predictive components to ensure progress on critical tasks.
B) Increase the frequency of Agile ceremonies to improve team communication.
C) Use hybrid project management techniques to integrate the best practices of both approaches.
D) Assign a separate team to handle the Agile components while the main team focuses on the predictive tasks.


Question 42:
A project manager is leading a project to develop a new IT system. The customer has requested several enhancements to the system, but the team is already struggling to meet the original schedule. How should the project manager handle this situation?

A) Reject the enhancements to avoid further delays.
B) Submit a change request and assess the impact on the project’s schedule and budget.
C) Ask the team to work overtime to accommodate the enhancements.
D) Incorporate the enhancements into the project and adjust the schedule later if needed.


Question 43:
A project manager has identified a critical risk that could potentially delay the project by several months. The project team has proposed several risk response strategies, but there is no consensus on the best approach. What should the project manager do?

A) Select the response that minimizes cost, as long as it also reduces the risk impact.
B) Facilitate a risk response meeting with key stakeholders to evaluate the options.
C) Choose the most conservative approach to minimize the impact of the risk.
D) Implement all proposed responses to ensure the risk is fully mitigated.


Question 44:
A project is nearing completion, and the project manager is preparing for the project’s closeout phase. However, the customer has requested a few additional changes that were not included in the original contract. What is the best course of action for the project manager?

A) Implement the changes to maintain a positive relationship with the customer.
B) Submit a change request and assess the impact on the project’s cost and schedule.
C) Refuse the changes, as they fall outside the original scope and contract.
D) Negotiate with the customer to defer the changes to a future project.


Question 45:
A project manager is conducting a lessons learned session at the end of a project. Several team members are reluctant to provide feedback due to fear of criticism. How can the project manager encourage open and constructive feedback?

A) Ensure that the feedback session is anonymous to protect team members.
B) Invite only key team members to the session to limit negative comments.
C) Encourage team members to focus only on positive aspects of the project.
D) Reassure the team that the feedback is for learning and improvement, not for assigning blame.


Question 46:
A project manager is working on a complex project with a large number of deliverables. The customer has asked for early delivery of one critical deliverable, but the project is already behind schedule. What should the project manager do?

A) Prioritize the critical deliverable and allocate additional resources to ensure early delivery.
B) Inform the customer that early delivery is not possible due to the project’s current status.
C) Submit a change request to assess the impact of delivering the critical deliverable early.
D) Negotiate with the customer to extend the overall project timeline in exchange for early delivery of the critical deliverable.


Question 47:
A project manager is managing a project using Scrum. During the daily stand-ups, the team frequently brings up issues that are not related to the sprint goal. This is causing the stand-ups to go over time. What should the project manager do?

A) Limit the discussion in the stand-up to issues directly related to the sprint goal.
B) Extend the time allocated for the stand-up to allow for additional discussion.
C) Allow the team to discuss all issues to promote open communication.
D) Schedule a separate meeting for non-sprint-related issues.


Question 48:
A project is facing significant delays due to a key team member leaving the project unexpectedly. What should the project manager do first?

A) Hire a replacement immediately to avoid further delays.
B) Assess the impact of the team member’s departure on the project schedule and budget.
C) Reassign tasks to other team members to keep the project on track.
D) Inform the project sponsor and request additional resources.


Question 49:
A project manager is preparing a project management plan and needs to determine the appropriate level of detail for the work breakdown structure (WBS). What is the most important factor to consider when determining the level of detail?

A) The complexity of the project tasks.
B) The experience level of the team members.
C) The time available to complete the WBS.
D) The project’s budget constraints.


Question 50:
A project is using a hybrid methodology with both predictive and Agile components. The project manager is finding it difficult to balance the needs of the two approaches. What should the project manager do to improve project execution?

A) Focus on the predictive components to ensure that all planned work is completed.
B) Use Agile principles to increase flexibility and adaptability in all areas of the project.
C) Create a hybrid project management plan that integrates the strengths of both approaches.
D) Assign a separate team to handle the Agile components to avoid delays in the predictive work.

Download the PMP question bank with answers pdf file from the below link.

pmp question bank
PMP Question Bank

PMP Exam Example Questions – Set 1

Preparing for the PMP exam requires a solid understanding of the project management principles outlined by PMI, along with practical application through PMP exam example questions. This resource provides a comprehensive question bank designed to help you tackle various PMP exam questions, including PMP sample questions, PMP practice questions, and scenario-based questions that mirror real exam conditions. With PMP mock tests, practice exams, and a variety of situational questions, you’ll be able to build your confidence and improve your problem-solving speed. Whether you’re looking for free PMP questions or an in-depth PMP test simulator, these example questions will support your PMP exam preparation and strengthen your grasp of essential knowledge areas. Dive into these PMP practice materials to excel in your certification journey.

Set 1

Question 1:
The project team identifies a risk that was not initially documented in the risk management plan. What should the project manager do next?
A Update the risk register and develop a mitigation strategy
B Escalate the risk to the project sponsor for action
C Ignore the risk since it was not identified during the planning phase
D Immediately inform all stakeholders of the new risk

Correct Answer: A
Explanation:
The correct response to any newly identified risk is to update the risk register and then work with the team to develop a mitigation strategy. Escalation or informing stakeholders should happen only after proper assessment.


Question 2:
A project manager finds that one of the contractors is falling behind schedule. What should the project manager do first?
A Replace the contractor with another one
B Review the contract terms and contact the contractor to discuss performance
C Inform senior management and request guidance
D Reduce the project scope to accommodate the delay

Correct Answer: B
Explanation:
The project manager should first address the performance issue by reviewing the contract and discussing it directly with the contractor. Escalating or reducing scope without an attempt to resolve the issue is premature.


Question 3:
During project execution, a team member suggests a minor change to improve a process. What is the best course of action for the project manager?
A Implement the change immediately to increase efficiency
B Submit a change request to evaluate the impact of the change
C Reject the change to avoid delays
D Document the suggestion and discuss it at the next project status meeting

Correct Answer: B
Explanation:
Even minor changes need to go through the change control process to assess any potential impact on scope, time, and budget before implementation. This ensures that all aspects are considered before taking action.


Question 4:
In a project closeout meeting, the sponsor expresses disappointment with some project deliverables despite all requirements being met. What should the project manager do?
A Dismiss the feedback since the project requirements were met
B Document the sponsor’s feedback as part of lessons learned
C Suggest revisiting the requirements to clarify any misunderstandings
D Request additional budget to modify the deliverables

Correct Answer: B
Explanation:
Documenting the sponsor’s feedback in the lessons learned register helps the team to improve future projects. This is a key aspect of continuous improvement.


Question 5:
A project manager finds that the team’s progress is significantly slower than anticipated. What should the project manager do to address this issue?
A Increase the team’s working hours
B Review the workload and reassign tasks to balance resource utilization
C Inform the stakeholders that the project will be delayed
D Conduct a team performance review to identify underperformers

Correct Answer: B
Explanation:
Re-evaluating and reassigning tasks is the best approach to balance resource usage and potentially speed up progress. Increasing hours or informing stakeholders without first trying to optimize resources may lead to team burnout or stakeholder dissatisfaction.

In conclusion, using PMP Exam Example Questions is a highly effective way to deepen your understanding and readiness for the PMP certification. By practicing with a variety of PMP Exam Example Questions, you’ll be more equipped to handle the diverse types of questions you’ll encounter on test day. Be sure to explore PMP Exam Example Questions in Set 2 of our question bank for additional practice, designed to enhance your project management knowledge and give you the confidence you need to succeed.