Diptish Sahoo

PMP Questions and Answers – Set 3, Ultra Tough PMP Question Bank Set

Below are 50 PMP Questions and Answers designed to help you prepare effectively for the exam. Explanations for all correct answers are provided at the end of the questions to enhance your understanding and boost your confidence.

1. During project initiation, the project sponsor asks for a summary of the financial justification for the project. Which document should you provide?

2. Which of the following is NOT typically a purpose of the project charter?

3. During stakeholder analysis, you identify a stakeholder who has high power but low interest. What is the recommended strategy for managing this stakeholder?

4. What is the primary benefit of the “identify stakeholders” process?

5. A project manager is tasked with ensuring the project aligns with organizational strategic goals. What document provides this alignment?

6. In an agile project, who is primarily responsible for prioritizing work items in the backlog?

7. Which of the following is typically a high-level deliverable created during project initiation?

8. Which input is necessary for the “develop project charter” process?

9. What is the primary output of the “define scope” process?

10. A project team is estimating activity durations using a three-point estimation technique. What is the formula for the PERT weighted average?

11. Which component of the project management plan defines how scope changes will be managed?

12. When developing a quality management plan, the team refers to organizational process assets. Which of the following would NOT be considered an organizational process asset?

13. During risk planning, you categorize risks based on their causes. This is an example of:

14. What is the primary goal of the Plan Procurement Management process?

15. A team is planning activities for an agile project and uses velocity as a key planning metric. What does velocity measure?

16. Which of the following is NOT an input to the “develop schedule” process?

17. What is the purpose of the risk register?

18. Which of the following is NOT a technique for defining project activities?

19. When is the stakeholder engagement plan developed?

20. A project manager is calculating the contingency reserve. What tool or technique would be most useful for this task?

21. What is the primary purpose of a daily stand-up in agile project management?

22. A project manager notices that team members are completing tasks but not updating the task status in the project management software. What should the project manager do?

23. During execution, a project manager discovers that a contractor has not met a key deliverable deadline. What is the project manager’s next step?

24. In agile projects, how are deliverables verified and accepted?

25. A conflict arises between two team members regarding task ownership. What is the project manager’s most appropriate action?

26. What is the primary focus of earned value management (EVM)?

27. A project has a cost performance index (CPI) of 1.1 and a schedule performance index (SPI) of 0.9. What does this indicate?

28. A team member informs the project manager that additional resources are needed to stay on schedule. What is the first action the project manager should take?

29. The control chart for a manufacturing process shows points that are outside the upper control limit. What does this indicate?

30. A project is tracking SPI and CPI values regularly. Which tool is the project manager using?

31. A key deliverable is rejected during a formal inspection. What is the best course of action for the project manager?

32. While performing qualitative risk analysis, you rank risks based on probability and impact. This approach:

33. A stakeholder requests additional functionality beyond the project’s approved scope. The project manager should:

34. What is the primary purpose of variance analysis in project monitoring?

35. The project manager receives a report showing CPI = 0.9 and SPI = 1.1. What should they prioritize?

36. A project manager notices that changes are being implemented without approval. What process is being bypassed?

37. During control quality, a project manager identifies a recurring defect in deliverables. What tool would help determine the root cause?

38. During project closure, the team realizes that an issue from execution remains unresolved. What is the best action?

39. What is the primary purpose of a final project audit?

40. In an agile project, the retrospective meeting serves what purpose?

41. Which document captures all details of project deliverables handed over to operations?

42. A project team has completed all deliverables, and the project sponsor signs off on final acceptance. What is the next step?

43. During a final stakeholder meeting, a key stakeholder expresses dissatisfaction with the project outcome. What should the project manager do?

44. Which activity is NOT part of the Close Project or Phase process?

45. What is a key benefit of a lessons learned register?

46. In an agile project, what is the primary role of the Scrum Master?

47. A product owner adjusts backlog priorities during a sprint. How should the Scrum Master respond?

48. Which of the following is an output of iteration planning?

49. In agile, what is the purpose of a “spike”?

50. During sprint reviews, the development team demonstrates completed features. Who is responsible for accepting these features?

PMP Questions and Answers

Download the PMP Questions and Answers PDF

Exit mobile version